Electricity & Water Authority




  • Project Name :
    Water Transmission Facilities for Bahrain Financial Harbour and Lulu Island and Al Futtaim Developments

  • Commencement Date :
    2009-06-23

  • Project Duration :
    36 Months

  • Start Date :
    2009-06-01

  • End Date :
    2013-06-01

  • Project Description :

    Underground Reservoir (Capacity 27.5 MLT), Elevated Storage Reservoir (Capacity 5.6 MLT), Pumping Station 520M2, Substation, Guard Room, Chlorination Building, Chambers, Manholes, draw pits, Surge Tank Foundations, Drainage works, Road works etc.