Ministry of Electricity & Water

Project Name:
Water Transmission Development

Commencement Date:
November 2013

Project Duration:
36 Months

Project Description:

This prestigious EPC project involves the construction of 2 New pumping stations, 3  ground storage tanks, 2 elevated storage reservoir and 1  concrete partially buried underground reservoir. Includes all associated civil, mechanical, SCADA and Telecom integration works.

Current Status October 2016

  •      All 3 x 5MIG GSTs at NBNT DS constructed, Electro-Mechanical, ICA equipments have been supplied, erected and the system is getting ready for commissioning.
  •      1 MIG ESR at NBNT DS is in advanced stage of completion
  •      Pumping Station at NBNT DS is getting ready for commissioning
  •      5 MIG GSR is in advanced stage of construction at Seef DS site
  •      1 MIG ESR is under construction at Seef ESR site
  •      Pumpset at Salmabad FS has been commissioned
  •      Pumpsets at Buquwah DS are under commissioning

Consultant : Mott Macdonald